     1.Before fixing the joist,make sure the ground are clean and flat.Puching holes in the installation area with impact

   drill.Recommended widthway and lengthway distance between 2 holes is 30cm,knock the expansion pipe into the 

   holes and make sure it is tight enough and will not expose.

 

     2.Take expansion pipes as centre line and lay joists on the line.Drill corresponding holes in the joist and fix the

   screws into the expansion pipes through the holes.

     3.Extro fixing of expansion blots are necessary on both joists near juncture.The holes should be at least 3cm 

   to the end of of joist.

 

     4.Allowing for the expansion and maintance,sufficiant distance around your terrace and by obstructions such as 

   walls,fences,trees.etc.sould be at least 3cm.

     5.Put first decking board on vertical way of joist,fasten the first decking board by strew(PS:not use clips)at

   outside the decking.The position and direction should be accurate guarrented to be the reference for the following

    decks.

 

     6.First deck should be fasten directly by screw instead of clips.

     7.Place the clip&strews in the right position and screw it,insert the second decking board into the clips then 

    repeat this process.

 

     8.Two joists are needed for each deck at the jointure.

     9.In case of the deformation caused by temperature change,Joists should not be too tightly connected.We recommend

   3cm distance between two two joists.

 

 

     10.Review of the whole decking system

     11.Fasten the external sides of the last decking the same way as first one.Install end cover anddecoration cover if

   necessary.